Factory Fence Letter Rust Removal and Refurbishment Record
Renovation of the large characters on the factory perimeter wall begins at the east corner. Last month, I inspected and found the steel letters rusting heavily with yellow streaks running down the wall; the strokes were bulging with flaking rust, and some corners were already severely degraded. The owner's directive was clear: preserve the existing characters—replacing them entirely would be too costly. Instead, we will focus on a thorough renovation involving rust removal and repainting to ensure a solid, durable finish. As key elements of the site signage, these perimeter wall characters serve as the face of the facility, but...
厂区围墙大字翻新从东墙拐角开干。上月去看,钢字锈得顺墙淌黄水,笔画鼓出锈皮,个别角位已经糟透。业主的意思很明确:字要留住,重新做一套太费钱,就把除锈喷漆的翻新账做扎实。厂区标识里,围墙大字是门面,可门面也得里子先过硬。这类活不显眼,周期又正好赶在厂区停产检修的窗口里,两不耽误。
动手前先把锈情分级。我们拿小锤逐字敲过去:声音实的是锈斑,打磨到位即可;锈皮鼓层的磨到露出铁色;敲着发空、钢板糟了的,局部割掉补焊加固,糟透的笔画按原样激光下料补块。锈穿的角位切下去,钢板薄得像纸,幸亏来得还不算晚。分级结果用粉笔写在字脚边上,锈斑区、补焊区、换块区一目了然,谁磨谁补各有分工。角磨机和针枪配合着走,边角和焊缝拿手工磨到位。除锈是慢工,省了这道,后头喷什么漆都白搭。
除锈当天就得封底,隔一夜闪锈又冒出来。底漆先走两道环氧富锌底漆,面漆用聚氨酯户外漆两道,每道间隔按干燥要求来,急不得。喷枪两遍成活,先薄后厚,头道盖底找平,二道出光;字腔内侧和背沿拿小笔刷补到,雨水冲的都是背后,防锈全靠这一笔。漆料进场前核了批次和出厂日期,过期漆再便宜也不收,调漆按当天用量现调,隔夜的余漆宁可作废。
户外漆面吃天气:湿度大不动枪,四级风以上停活,排期表提前一周圈出天气窗口。色号按原厂色卡比对,我们在现场喷了小样块,让老板对着旧字认过,才批量往下走。
脚手架沿墙搭设,靠路一侧全封闭围挡,底部压沙袋,围挡网眼挂防尘布,漆雾不外飘。翻新改色之外还有配套活:墙面淌过的锈痕用同系列外墙漆收掉,字脚松动的补栓加固,背架焊点逐一复查做防锈,缺笔画的位置补完打磨接色,新旧漆交界拿细砂纸打毛再过渡,远看一个色,近看不留痕。字与墙之间的垫块也换了一批,碎掉的水泥垫换成尼龙垫块再上帽,雨水积不住。
一周多收工,夜里打灯看剪影,笔画边缘发乌的地方再补一道。业主绕墙走了一圈,提了个边角,当场记下,次日补完拍了回传照片;他说这套字陪厂区搬过一次门牌,留着踏实,我们应下来,翻新可以,形不许走样。没动原字结构,费用比重新做字省下一大截,工序却一道没少——围墙大字翻新的账就是这么算:省下的钱,是提前花在对的工序上的工。